Invergordon Dock had experienced a number of projects involving offshore equipment which had arrived to have large scale refurbishment but had suffered from unplanned costs and delays due to poor weather and the environmental responsibilities attached to  the industrial blasting and painting process.

A solution was required to ensure both weather protection and the environmental conditions could be controlled.

Industrial Shrink Wrap material was the only suitable material capable of containing such a large area providing material containment and weather protection of this scale.

VERISAFE 300 Micron FR materials were used to contain the projects and a technical installation to cope with high wind speeds experienced daily.

15,000m2 and 10 weeks installation period.